Construction Update: April 23, 2025

🚨NEW DATES🚨
CONSTRUCTION UPDATE: April 23, 2025
Updated lane closure schedule on northbound Van Buren Boulevard: On Thursday, April 24, the closure is canceled. Work will now take place Friday, April 25, through Wednesday, April 30, from 5 a.m. to 4 p.m., excluding Saturday and Sunday.
TRAFFIC IMPACTS:
Northbound Van Buren Boulevard (Limonite Avenue to Rutile Street)
Friday, April 25 – Wednesday, April 30
5 a.m. to 4 p.m. (No work Saturday or Sunday)
- Closure needed for oversized truck deliveries
- Crews continuing railroad track work
- Reduce speeds and watch for large trucks in the area
This information may change due to weather or field conditions.
Plan ahead, expect delays, and use alternate routes when possible.
Construction Hotline: 800-679-9570
More info: www.JurupaGradeSeparation.com
Construction Alert: Week of April 21, 2025


CONSTRUCTION ALERT: Week of April 21, 2025
Single lane closure on northbound Van Buren Blvd. continues April 23–25; plan for delays in the area
TRAFFIC IMPACTS:
Northbound Van Buren Blvd (Limonite Ave to Rutile St)
Wednesday, April 23 – Friday, April 25
5 a.m. to 4 p.m.
- Closure needed for oversized truck deliveries
- Crews delivering materials for railroad track work
- Reduce speeds and watch for large trucks in the area
This information may change due to weather or field conditions.
Plan ahead, expect delays, and use alternate routes when possible.
Construction Hotline: 800.679.9570
More info: www.JurupaGradeSeparation.com
Updated Construction Alert: Week of April 14, 2025

‼️ NEW DATES ‼️
CONSTRUCTION ALERT: Week of April 14, 2025
⚠️ Lane closures planned on northbound Van Buren; watch for large trucks traveling through the project area
TRAFFIC IMPACTS: Northbound Van Buren Blvd (Limonite Ave to Rutile St)
Wednesday, April 16 – Friday, April 18
5 a.m. to 4 p.m.
– The closures are necessary for oversized trucks to deliver construction materials to continue work on the railroad track
– Reduce speeds and watch for large trucks in the area
This information may change due to weather or field conditions.
Plan ahead, expect delays, and use alternate routes when possible.
Construction Hotline: 800.679.9570 More info: www.JurupaGradeSeparation.com
#JurupaGradeSeparation #JurupaValley #JurupaValleyTraffic
Construction Alert: Week of April 14, 2025

Construction Alert: Lane closures planned on northbound Van Buren; watch for large trucks traveling through the project area
TRAFFIC IMPACTS
Lane closures are planned on northbound Van Buren Boulevard from north of Limonite Avenue through Rutile Street. Tuesday, April 15 through Friday, April 18 5 a.m. to 4 p.m. Please plan for delays and use alternate routes when available.
The closures are necessary for oversized trucks to deliver construction materials to continue work on the railroad track.
Please reduce speeds and watch for large trucks traveling through the project area.
This information may change due to weather or field conditions.
Hotline: 800.679.9570
Construction Alert: Week of April 7, 2025


CONSTRUCTION ALERT: Temporary lane closures at Jurupa and Pedley roads starting this week. The intersection remains open.
TRAFFIC IMPACTS
– Monday–Friday | 7 a.m.–4 p.m.
– Lane closures needed for traffic signal installation
– The new signal is expected to be operational by the end of April
Plan for possible delays and drive with caution through the area.
Hotline: 800.679.9570
Behind The K-Rail


Behind the Krail: Work continues on Felspar Street at Jurupa Road through the week of March 24.
TRAFFIC IMPACTS
Lane closure on Felspar Street
Monday – Friday
6 a.m. to 4 p.m.
Please drive with caution and reduce speed through the construction zone.
BUSINESS ACCESS REMAINS OPEN
——————————————————————–
Tras el Krail: Las obras continúan en la calle Felspar con Jurupa Road durante la semana del 24 de marzo.
IMPACTOS EN EL TRÁFICO
Cierre de carril en la calle Felspar
Lunes a viernes
De 6:00 a.m. a 4:00 p.m.
Conduzca con precaución y reduzca la velocidad en la zona de construcción.
EL ACCESO COMERCIAL PERMANECE ABIERTO
Construction Update


Construction Update: Week of March 17
Single lane closures resume on Felspar Street at Jurupa Road and continue through March.
TRAFFIC IMPACTS
Lane closure on Felspar Street
Monday – Friday
6 a.m. to 4 p.m.
Please drive with caution and reduce speed through the construction zone.
——————————————————————–
Actualización de la Construcción: Semana del 17 de marzo
Se reanuda el cierre de un solo carril en la calle Felspar con Jurupa Road hasta marzo.
IMPACTOS EN EL TRÁFICO
Cierre de un solo carril en la calle Felspar
Lunes a viernes
6:00 a.m. a 4:00 p.m.
Conduzca con precaución y reduzca la velocidad en la zona de construcción.
Construction Update


Work postponed on Felspar Street at Jurupa Road due to weather
TRAFFIC IMPACTS
Please watch for traffic delineators and drive with caution through the construction zone.
BUSINESS ACCESS REMAINS OPEN.
Actualización de la construcción: semana del 10 de marzo
Se pospuso el trabajo en Felspar Street Y Jurupa Road debido a el clima
IMPACTOS EN EL TRÁFICO
Favor de estar atento a los demarcadores y conduzca con precaución por la zona de construcción.
EL ACCESO A LOS NEGOCIOS PERMANECE ABIERTO.
Construction Update



Construction Update: Single Lane closures will remain in effect on Felspar Street at Jurupa Road through March as crews continue installing underground utilities.
Please drive with caution as crews will be closing a lane in one direction at a time and shift traffic. One lane of traffic will remain open in both directions.
TRAFFIC IMPACTS
Single lane closures on Felspar Street
Monday – Friday
6 a.m. to 4 p.m.
Please drive with caution and reduce speed through the construction zone.
BUSINESS ACCESS REMAINS OPEN.
Actualización de la construcción: Los cierres de carriles únicos permanecerán vigentes en Felspar Street y Jurupa Road hasta marzo mientras las cuadrillas continúan instalando servicios subterráneos.
Conduzca con precaución ya que las cuadrillas cerrarán un carril en una dirección a la vez y cambiarán el tráfico. Se mantendrá abierto un carril de circulación en ambos sentidos.
IMPACTOS DEL TRÁFICO
Cierres de carril único en Felspar Street
Lunes – Viernes
6 a.m. a 4 p.m.
Conduzca con precaución y reduzca la velocidad en la zona de construcción.
EL ACCESO COMERCIAL PERMANECE ABIERTO.
Construction Update


Construction Update: Single Lane Closures continue on Felspar St. at Jurupa Rd. through March as crews work on installing underground utilities.
TRAFFIC IMPACTS
Monday to Friday
6 a.m. to 4 p.m.
Daytime lane closures continue on Felspar St. at Jurupa Rd. Crews will close a lane in one direction at a time and shift traffic. One lane of traffic will remain open in both directions.
BUSINESS ACCESS REMAINS OPEN.
This information may change due to weather or field conditions.
Actualización de construcción: Continúan los cierres de carriles únicos en Felspar St. en Jurupa Rd. hasta marzo, mientras las cuadrillas trabajan en la instalación de servicios públicos subterráneos.
IMPACTOS DEL TRÁFICO
Lunes a viernes
6 a.m. a 4 p.m.
Los cierres de carriles durante el día continúan en Felspar St. y Jurupa Rd. Los equipos cerrarán un carril en una dirección a la vez y cambiarán el tráfico. Se mantendrá abierto un carril de circulación en ambos sentidos.
EL ACCESO COMERCIAL PERMANECE ABIERTO.
Esta información puede cambiar debido al clima o las condiciones del campo.