Project Update

Current Update | Actualizacion Actual

June 28, 2024 | Junio 28, 2024

All roads open in the project area. 

First Photo: Crews completed a portion of the storm drain system installation at the intersection of Jurupa and Pedley roads and postponed the remainder of the work due to utility conflict discovered during the intersection closure. 

Primera Foto: Las cuadrillas completaron una parte de la instalación del sistema de drenaje pluvial en la intersección de las carreteras Jurupa y Pedley y pospusieron el resto del trabajo debido a un conflicto de servicios públicos descubierto durante el cierre de la intersección.

Second Photo: Crews are installing a waterline under Van Buren Blvd. and the railroad tracks. The underground work is being completed behind k-rail from the east side of the intersection of Van Buren Boulevard south of Jurupa Road. This will not affect traffic and will be completed in late August, 2024.

Segunda Foto: Las cuadrillas están instalando una línea de agua debajo de Van Buren Blvd. y las vías del ferrocarril. El trabajo subterráneo se está completando detrás del carril K desde el lado este de la intersección de Van Buren Boulevard al sur de Jurupa Road. Esto no afectará el tráfico y se completará a finales de agosto de 2024. 

Business Access Remains Open | Acesso a Negocios Habierto